Raumfahrt - ESA lays out roadmap to Vega-C and Ariane 6 flights

31.10.2020

artist-s-view-of-ariane-6-and-vega-c-pillars

Vega-C and Ariane 6 are being developed by ESA to assure Europe’s independent access to space. The maiden flight for Vega-C is planned to take place in June 2021, and that for Ariane 6 in the second quarter of 2022.

Solid progress is being made on both Vega-C and Ariane 6 development programmes. Since March, some technical events and the COVID-19 pandemic have both impacted the progress of activities. Uncertainty from COVID-19 still persists globally to date.

Vega-C

Artist's view of Vega-C on the launch pad
Artist's view of Vega-C on the launch pad

Vega-C is a more powerful and versatile version of the Vega launch vehicle currently operating at Europe’s Spaceport in French Guiana.

Vega was on track for its return to flight, after the July 2019 failure, with its mission (VV16) in March 2020, but Europe’s Spaceport had to be closed due to COVID-19 safety measures. The VV16 launch campaign resumed in May but several further launch attempts were halted due to unfavourable weather. Vega’s return to flight, with the new SSMS dispenser carrying 53 satellites, was successfully launched on 2 September.

Between February and September no activities for the preparation of Vega-C were possible in the Vega mobile gantry while it housed the P80 solid rocket motor in readiness for flight VV16, due to safety constraints.

The qualification at system and subsystems level is currently under finalisation.

P120C motor hot firing
P120C motor hot firing

As from October, all the new solid motors for Vega-C have completed qualification testing. The Zefiro-40 solid rocket motor for Vega-C completed qualification tests in 2019. The final test of the P120C took place successfully on 7 October.

Two Vega flights, VV17 and VV18, are planned before Vega-C. Activities for the modification of the mobile gantry for Vega-C, such as modifications of the fluids networks as well as connection and installation of the new control bench for Vega-C, will have to start after VV18 now planned early February.  

Vega-C maiden flight is planned for June 2021.

Vega-C is a project managed and funded by the European Space Agency. Avio is the industrial prime contractor. Arianespace commercialises Vega-C.

Ariane 6

Ariane 6 using four P120C boosters
Ariane 6 using four P120C boosters

ESA, CNES and ArianeGroup have jointly established a consolidated reference planning for Ariane 6 development and are working as an integrated team in their respective roles to make it happen. This schedule is based on analysis of recent achievements, remaining critical milestones and the impact on the programme caused by the COVID-19 pandemic.

With the successful third static fire test of the P120C solid rocket motor on 7 October, all the propulsion elements of the launcher system have completed their qualification tests.

Booster and core stage mockups inside mobile gantry
Booster and core stage mockups inside mobile gantry

At Europe’s Spaceport, activities for the finalisation of the Ariane 6 launch base are progressing. First integration testing with fullscale ‘mock-ups’ of the P120C strap-on booster and of Ariane 6’s central core took place in the new mobile gantry. Testing of the cryogenic arms that link the launch pad and the launch vehicle are also ongoing at Fos-sur-Mer in France, before shipping to French Guiana.

ArianeGroup is completing the challenging development and qualification of the Ariane 6 Auxiliary Power Unit for the upper stage. This device will allow Europe to offer additional capabilities in satellite deployment for the satellite constellation market.

P5.2 test facility simulates launch for Ariane 6 upper stage
P5.2 test facility simulates launch for Ariane 6 upper stage

The first Ariane 6 upper stage has been assembled in Bremen, Germany. Coupling the launcher’s tanks with the equipped engine bay of the re-ignitable Vinci engine for the first time. The upper stage is currently undergoing mechanical, fluid and electrical tests, before leaving for further tests at the DLR German Aerospace Center’s Lampoldshausen facilities in Germany.

There, the complete stage will be hot fire tested on a new test bench specially developed by DLR for the Ariane 6 upper stage. The Ariane 6 upper stage static fire tests are planned to start in the second quarter of 2021.

Ariane 6 core stage mockup in the assembly building at Europe's Spaceport
Ariane 6 core stage mockup in the assembly building at Europe's Spaceport

In parallel, the first Ariane 6 core stage and the second Ariane 6 upper stage are under preparation. These specimen will be shipped to Europe’s Spaceport from Les Mureaux (France) and Bremen (Germany) respectively, for the combined tests campaign.  

In the third quarter of 2021, the Ariane 6 launch base will be handed over from CNES to ESA. At this point the Ariane 6 combined tests campaign can start. These series of tests will bring the launch vehicle and launch base together for the first time for integrated tests of multiple systems. This will include a static fire test of Ariane 6 while standing on the launch pad for the first time.

Practising integration on the launch pad
Practising integration on the launch pad

Following the successful combined test campaign and Ground qualification review of the launch system, the first launch campaign, with the integration of the maiden flight hardware, will start.

When all these steps are successfully completed Ariane 6 will be in a position to perform its maiden flight in the second quarter of 2022.

Ariane 6 is a project managed and funded by the European Space Agency. ArianeGroup is design authority and industrial prime contractor for the launcher system. The French space agency CNES is prime contractor for the development of the Ariane 6 launch base at Europe’s Spaceport in French Guiana. Arianespace commercialises Ariane 6.